The NWSC-3 project team and HPE engineers continued working through the Acceptance Testing Phase (ATP) and encountered several functional and resiliency issues. They are working with HPE subject matter experts on fixing issues the team faced while testing. A second power-down and power-up test for all of Derecho and its storage system is planned for this week. 

When functional and resilience testing is completed, the project team will prepare Derecho for benchmarking and availability testing. 

NWSC-3 project team member Summer Wasson created this time-lapse video of the installation.